(Lander, WY) – The City of Lander and High Country Construction have shared the following Lincoln Street construction project update for this week, going into next.
What’s Happening This Week:
- Paving of the 100 block through the 2nd Street intersection
- Road base placement on 200 block
- Reopening of the 2nd Street intersection and 100 block before the 4th of July holiday
What’s Happening Next Week:
- Crews will begin removing asphalt on the 300-400 block
Reminders:
- Please use caution around the work site
- Area businesses remain open and appreciate your continued support
If you are a business or property owner in the construction area and have any questions, please do not hesitate to reach out to Nicholas Newman with High Country Construction at 307-330-7161.