(Lander, WY) – The City of Lander and High Country Construction have shared the following Lincoln Street construction project update for this week, going into next.

What’s Happening This Week:

  • Paving of the 100 block through the 2nd Street intersection
  • Road base placement on 200 block
  • Reopening of the 2nd Street intersection and 100 block before the 4th of July holiday

What’s Happening Next Week:

  • Crews will begin removing asphalt on the 300-400 block

Reminders:

  • Please use caution around the work site
  • Area businesses remain open and appreciate your continued support

If you are a business or property owner in the construction area and have any questions, please do not hesitate to reach out to Nicholas Newman with High Country Construction at 307-330-7161.  