#HeadsUp: Pavement improvement project starts this week near Crowheart

This #headsup is brought to you by Bailey’s Tire and Auto Service.

A $5.82 million pavement improvement project is scheduled to begin Wednesday, May 24, on US26/287 near Crowheart.

The project includes asphalt pavement surfacing, milling, chip sealing, traffic control and other work on 12.9 miles of US26/287 between mileposts 72.13 (about 16 miles southeast of Dubois) and 85.03 (14 miles northwest of Diversion Dam Junction).

Prime contractor on the project is McGarvin-Moberly Construction Co., of Worland.

“The contractor’s schedule calls for asphalt milling beginning Wednesday, with single-lane traffic led through the project by pilot vehicle until about dark,” said Wyoming Department of Transportation resident engineer Robert Scheidemantel of Riverton. “Motorists should expect 20-minute traffic delays with stopped conditions and a milled driving surface starting this week.”

More than 36,000 tons of asphalt paving are scheduled to begin June 9, with chip sealing of the highway scheduled after the July 4 holiday.

The Wyoming Transportation Commission awarded the bid to McGarvin-Moberly, in May 2022. Contract completion date is Aug. 31, 2023.